Government reveals taxpayer-funded deal to keep Australia’s largest aluminium smelter open. How long we will pay?

  • Written by Tony Wood, Program Director, Energy, Grattan Institute




It seemed inevitable – politically at least – that the federal government would step in to save Tomago Aluminium in New South Wales, Australia’s largest aluminium smelter.

Rio Tinto, the owners of Tomago, has enjoyed attractively priced electricity for a long time, most recently with AGL. But this contract ends in 2028. Unable to find a replacement at a price it could accept, Rio Tinto warned that Tomago was facing closure. Tomago produces more than one-third of Australia’s aluminium and accounts for 12% of NSW’s energy consumption.

On Friday, Prime Minister Anthony Albanese announced a Commonwealth-led deal for electricity supply beyond 2028. This deal will provide the smelter with billions of dollars[1] in subsidised power from the Commonwealth-owned Snowy Hydro through a portfolio of renewables, backed by storage and gas. This follows months of negotiation to avoid the smelter closing and sacking its roughly 1,000 workers.

The government has provided funding to support other struggling manufacturers such as the Whyalla steelworks[2] and the Mount Isa copper smelter[3], and wants to see aluminium production continue in Australia. About 30–40% of the cost of making aluminium is the energy, so it’s a huge input. Electricity from the market would have been considerably more expensive, so the government is subsidising the commercial price.

The deal may have been a necessary and immediate solution to a political problem with local economic and social impacts. However, it raises several important questions about the risks involved and the longevity of the plant.

Risks and benefits

First, to what risk is the federal government exposed? Commodity markets such as aluminium are prone to difficult cycles, and there’s a chance Tomago might not survive at all, in which case the government is off the hook.

Not only are we looking to subsidise Tomago’s electricity, but we are looking for Snowy Hydro to invest in renewable energy projects and build more renewable energy in NSW. The history of building renewable energy and its support transmission infrastructure suggests that both cost and time constraints become problematic. The NSW government may have a role in supporting this side of the deal.

The Commonwealth’s case for making this deal is presumably underpinned by its Future made in Australia[4] policy. This says we should be supporting industries where there’s a national interest in a low-emissions world. So if, for example, we can see a future where subsidising Tomago’s electricity for five or ten years would mean it can produce low-emission aluminium the world wants to buy, that would be a success.

But what happens if, after five or ten years, the world hasn’t sufficiently changed to provide enough renewable energy to make our electricity cost less? What if the rest of the world wants green, low-emissions aluminium, but that’s not what Australia produces? If the risks the government is underwriting crystallise in a bad way, does the government have an exit strategy?

Aluminium stored at the Tomago smelter.
Aluminium stored at the Tomago smelter. Michael Gorton/AAP

We’ve been here before

In 1984, under the leadership of John Cain, the Labor government signed a joint venture agreement[5] with Alcoa to build an aluminium smelter at Portland, including a deal to subsidise electricity until 2016. Forty years later, we’re still pay for it.

With Tomago, we don’t want Australian taxpayers exposed to something over which we have no control – the global price of aluminium. If the price of aluminium collapses, or Snowy Hydro is permanently uncompetitive or China dominates the world market, the hypothesis that Tomago can be competitive in the long term collapses.

Interestingly, this deal is very different to the one the Commonwealth and Queensland governments have done to support Rio Tinto’ Boyne smelter in Gladstone.

In October, Rio Tinto announced plans to possibly bring forward the closure[6] of Gladstone Power Station to 2029, six years ahead of the current schedule, and supply the smelter with predominantly renewable electricity. The move was welcomed by environmental groups, as Gladstone is Queensland’s oldest and largest coal-fired station.

But some commentators have said closing the plant in four years’ time is unrealistic[7], and a staged phase-out would be better.

The announcement this week, welcomed by the business and its workers, is probably unsurprising. But we haven’t seen the detail. The government may very well have a case for this deal, but the future of the plant and its power supply remain unknowable. The risks with taxpayer funds may have been worth taking, but they should be clearly explained and justified.

References

  1. ^ billions of dollars (www.afr.com)
  2. ^ Whyalla steelworks (theconversation.com)
  3. ^ Mount Isa copper smelter (theconversation.com)
  4. ^ Future made in Australia (treasury.gov.au)
  5. ^ joint venture agreement (en.wikipedia.org)
  6. ^ bring forward the closure (theconversation.com)
  7. ^ is unrealistic (theconversation.com)

Read more https://theconversation.com/government-reveals-taxpayer-funded-deal-to-keep-australias-largest-aluminium-smelter-open-how-long-we-will-pay-271943

Times Magazine

AI threatens to eat business software – and it could change the way we work

In recent weeks, a range of large “software-as-a-service” companies, including Salesforce[1], Se...

Worried AI means you won’t get a job when you graduate? Here’s what the research says

The head of the International Monetary Fund, Kristalina Georgieva, has warned[1] young people ...

How Managed IT Support Improves Security, Uptime, And Productivity

Managed IT support is a comprehensive, subscription model approach to running and protecting your ...

AI is failing ‘Humanity’s Last Exam’. So what does that mean for machine intelligence?

How do you translate ancient Palmyrene script from a Roman tombstone? How many paired tendons ...

Does Cloud Accounting Provide Adequate Security for Australian Businesses?

Today, many Australian businesses rely on cloud accounting platforms to manage their finances. Bec...

Freak Weather Spikes ‘Allergic Disease’ and Eczema As Temperatures Dip

“Allergic disease” and eczema cases are spiking due to the current freak weather as the Bureau o...

The Times Features

5 Cool Ways to Transform Your Interior in 2026

We are at the end of the great Australian summer, and this is the perfect time to start thinking a...

What First-Time Buyers Must Know About Mortgages and Home Ownership

The reality is, owning a home isn’t for everyone. It’s a personal lifestyle decision rather than a...

SHOP 2026’s HOTTEST HOME TRENDS AT LOW PRICES WITH KMART’S FEBRUARY LIVING COLLECTION

Kmart’s fresh new February Living range brings affordable style to every room, showcasing an  insp...

Holafly report finds top global destinations for remote and hybrid workers

Data collected by Holafly found that 8 in 10 professionals plan to travel internationally in 202...

Will Ozempic-style patches help me lose weight? Two experts explain

Could a simple patch, inspired by the weight-loss drug Ozempic[1], really help you shed excess k...

Parks Victoria launches major statewide recruitment drive

The search is on for Victoria's next generation of rangers, with outdoor enthusiasts encouraged ...

Labour crunch to deepen in 2026 as regional skills crisis escalates

A leading talent acquisition expert is warning Australian businesses are facing an unprecedented r...

Technical SEO Fundamentals Every Small Business Website Must Fix in 2026

Technical SEO Fundamentals often sound intimidating to small business owners. Many Melbourne busin...

Most Older Australians Want to Stay in Their Homes Despite Pressure to Downsize

Retirees need credible alternatives to downsizing that respect their preferences The national con...