Clarke Energy to Engineer, Procure and Construct an expansion and upgrade of Alinta Energy's gas-fired Newman Power Station in Western Australia's Pilbara region

- Fourteen high-efficiency INNIO Jenbacher J624 gas engine generators to provide 60MWe of capacity

- Clarke Energy to design and construct two separate power houses and supply a 66/11kV export transformer complete with brownfield integration with existing 66kV substation

- The expansion will support Alinta's operations in the Pilbara

NEWMAN, Australia, Sept. 4, 2020 /PRNewswire/ -- Clarke Energy and INNIO announced that Clarke Energy, INNIO's distributor and service partner for Jenbacher gas engines, will provide 14 high-efficiency Jenbacher J624 gas engines to improve the efficiency and flexibility of Alinta Energy's gas-fired Newman Power Station in Western Australia's Pilbara region.

Alinta Energy's gas-fired Newman Power Station to be expanded by Clarke Energy Alinta Energy's gas-fired Newman Power Station to be expanded by Clarke Energy

60MW of gas-fired generation will support Alinta Energy's Pilbara operations, including the Chichester Solar Gas Hybrid project (comprising 60MW of solar photovoltaic generation and 60kms of transmission line), when complete.

Clarke Energy will deliver the Engineering, Procurement and Construction (EPC) for the new gas fired power generation facility which will utilise the Jenbacher J624 generators, each with a capacity of 4.41 MW, providing a total capacity of 61.67MW[e]

The 4.4MW engines are well suited to this application providing a flexible combination of turn-down, efficiency and the rapid load response required for integration with solar. The Jenbacher J624 gas engines are also more compact than others, which will help to reduce the risks of working at heights present with larger models.

Alinta Energy's Executive Director Merchant Energy, Ken Woolley, said he was pleased to welcome Clarke Energy to the project:

"Safety is number one for us and Clarke Energy has a solid track record of safely providing high quality solar and gas fired power integration solutions.

"Their technical expertise will also be critical to help us deliver on a very exciting program of work in the region," he said.

Clarke Energy will design and construct two separate power houses, with cooling radiators at mounted roof level due to the limited space constraints of the Newman Power Station site. The Clarke Energy scope of work also includes supply of a 66/11kV export transformer and brownfield integration with the existing 66kV substation.

Following completion of the EPC works, Clarke Energy will operate and maintain the facility for Alinta Energy under a long-term contract utilising their team of factory trained service technicians and operators.

Managing Director of Clarke Energy, Greg Columbus, commented:

"As an industry-leading EPC contractor and OEM Distributor for Jenbacher Gas Engines with a long history of delivering clean power solutions, we are very pleased to have been chosen to increase the reliability and efficiency of the Newman Power Station. The Jenbacher J624 high-speed, high-efficiency and dependable gas engine technology fits well with Alinta Energy's need to provide reliable, efficient power while having minimal environmental impact. The completion of this project will increase the capacity of Jenbacher gas engines installed in the region to ~900MW."

About Alinta Energy

Alinta Energy is a leading Australian utility with an owned and contracted generation portfolio exceeding 3,000MW, over 700 employees across Australia and New Zealand and over 1,100,000 combined electricity and gas retail customers across Western Australia, South Australia, Victoria, New South Wales and Queensland. Alinta Energy have been supplying energy to homes and businesses in Australia for over 20 years. 

As part of its growing energy portfolio, Alinta Energy owns and operates power stations across Australia including the Port Hedland, Newman, Pinjarra and Wagerup Power Stations in Western Australia. In the eastern states, it operates the Braemar Power Station (QLD) and Bairnsdale Power Station (Vic). Alinta Energy also has several long-term offtakes in place in key markets in which it operates, including Loy Yang B Power Station (Vic), Yandin Wind Farm (WA) and a range of other renewable, solar and wind, facilities.

With a goal to deliver low emission energy that's reliable and affordable, Alinta Energy has committed to a 2025 target of 1,500MW of owned and contracted renewable energy generation to be achieved through innovative and high-quality projects.

About Clarke Energy

Clarke Energy – a KOHLER Company - is a leader in the engineering design, installation and long-term maintenance of gas engine-based power plants. The company is an authorised sales and service provider for INNIO's Jenbacher gas engines in 25 countries. Clarke Energy employs over 1,200 staff and has over 7,000 MW of Jenbacher generation equipment installed in its operational areas.

In Australia, Clarke Energy has been distributing Jenbacher gas engines Australia and New Zealand since 1999. During this time, over 400 gas engines (900 MW) have been installed across industries including mining, water, waste management, oil and gas and manufacturing.

Clarke Energy's South Pacific Head Office, located in Adelaide, employs over 60 people locally with another 80+ across all states of Australia and in New Zealand servicing the installed fleet. Locally it also houses an extensive parts warehouse to service the growing Jenbacher and KOHLER reciprocating engine business.

www.clarke-energy.com | Twitter: @ClarkeEnergy | LinkedIn | Facebook[1][2][3][4]

Photo - https://mma.prnasia.com/media2/1248904/clarke_energy_alinta_energy_newman_power_station.jpg?p=medium600[5]

References

  1. ^ www.clarke-energy.com (www.clarke-energy.com)
  2. ^ @ClarkeEnergy (twitter.com)
  3. ^ LinkedIn (www.linkedin.com)
  4. ^ Facebook (www.facebook.com)
  5. ^ https://mma.prnasia.com/media2/1248904/clarke_energy_alinta_energy_newman_power_station.jpg?p=medium600 (mma.prnasia.com)

Read more https://www.prnasia.com/story/archive/3115305_AE15305_0

Business Times

Scam Prevention Must Become a Business Resilience Priority

As Australia marks Scam Awareness Week, organisations are being urged to rethink their approach to scam prevention ...

What Insurance Customers Really Want from Omnichannel Communicati…

Despite years of investment in digital engagement, from rolling out mobile apps and online portals to digital communication...

Times Media Group launches four new Australian local publications…

ByronBay.au, TheCairnsTimes.com.au, AirlieTimes.com.au and NoosaTimes.com have been launched as part of an expanding networ...

Technology

China copied the Falcon 9 formula. …

China has spent years watching SpaceX transform the economics of spaceflight. Now it is beginning...

Local News

Psychology clinic in Tasmania opens…

In response to Tasmania’s growing mental health crisis, a new purpose-built, multi-disciplinary me...

Culture

He Won't Buy It Himself. That's Exa…

Dads can be notoriously difficult to buy for. They will insist they do not need anything, then conti...

Travel

Cairns Esplanade Lagoon — the stage where Cai…

“All the world's a stage.” Shakespeare wasn't writing about Cairns when he penned that famous lin...

The Times Features

He Won't Buy It Himself. That's Exactly Why I…

Dads can be notoriously difficult to buy for. They will insist they do not need anything, then conti...

The Supports Are Working — They Are Not Optional

When I work, live in supported accommodation and take part in my community, that is evidence the NDI...

Mundi Mundi Bash: You Are Not Just Watching the Show — …

Come to the Mundi Mundi Bash for the music and you soon discover something unexpected: the concert...