The government just killed 50 infrastructure projects – what matters is whether it will fund them on merit from now on

The federal government has just announced a list[1] of projects to be abandoned as a result of an independent strategic review[2] of its infrastructure investment program.

The review found the cost of the A$120 billion, ten-year program had blown out by $32.8 billion[3], half of which was in projects not yet under construction.

But the flaws in national infrastructure planning go much deeper than the question of whether or how projects are listed on a spreadsheet, and how much their costs blow out.

A national framework built around Infrastructure Australia[4] was supposed to resolve differences between the states and the federal government on projects before they get approved.

Read more: Infrastructure review recommends culling 82 planned projects[5]

In the late 1990s and early 2000s, as Australia was recovering from recession, demands for new infrastructure funding grew.

Sydney, which had been “full up[6]” according to then NSW Premier Bob Carr and had economised on spending in the runup to the 2000 Olympics, desperately needed new infrastructure.

With their budgets constrained, states began pitching projects to the federal government, but incoherently and without a national framework.

The Rudd Labor government went to the 2007 election promising to bring coherence and rationality to national infrastructure planning.

Independent advice was meant to fix things…

Rudd and the then infrastructure minister Anthony Albanese established Infrastructure Australia as an independent statutory authority to provide advice on national needs and project priorities. The idea of it being independent came from technocratic bodies such as the Reserve Bank and the Productivity Commission.

Infastructure Australia was diligent in its approach.

It undertook national infrastructure audits to determine key areas of need, prepared uniform criteria by which projects should be assessed, and compiled priority lists of projects assessed on merit against those criteria.

Final decisions on funding would rest with ministers, but they would have the benefit of Infrastructure Australia’s independent advice.

…but big projects are inherently political

But large infrastructure projects addressing public and business needs are unavoidably political.

As desirable as an independent body assessing projects on merit seems, retail politics militate strongly against delegating decisions to technocratic bodies.

But conversely, a minister who is seen to reject official independent advice is politically exposed. This gives both the agency and the minister strong imperatives to preserve each other’s modesty.

From the mid-2010s to the early 2020s, the Australian public service became increasingly politicised, resulting in hollowing out of expertise, loss of independence, and scandals such as robodebt[7].

‘High priority’ versus mere ‘priority’

Infrastructure Australia, while independent of the core public service in the same way as is the Reserve Bank, became subject to political pressure.

This is exemplified by the case of Victoria’s East-West Link toll road. The Abbott Commonwealth government committed to the project[8] ahead of the 2014 Victorian election, despite the project having a benefit-cost ratio of less than one[9], meaning that its benefits were less than its costs.

Under the pressure to resolve the contradiction, Infrastructure Australia created a “high priority[10]” list in addition to its existing “priority[11]” list.

The new “high priority” list would include only the projects assessed as having the greatest value to the nation. The existing repurposed “priority” list could house the politically important but less meritorious projects, allowing politicians to claim these projects were “priorities”, even if their absolute merit was doubtful.

East-West Link funded then cancelled

East West Link: unpopular and found not to be worth the cost. Julian Smith/AAP[12]

The 2014 Victorian election result rescued some modesty after the newly elected Dan Andrews abandoned[13] the East-West Link, but the interplay between political needs and technical rationality has if anything gotten worse.

Andrews’s $200 billion Suburban Rail Loop[14] was endorsed electorally at the 2018 and 2022 state elections despite not appearing in any formal metropolitan or statutory transport plans.

At the time of the 2022 federal election, it hadn’t been submitted to Infrastructure Australia for assessment. But the federal Labor opposition, now the government, committed $2.2 billion[15] to it.

Victoria has since submitted the Suburban Rail Loop to Infrastructure Australia, but the assessment is unfinished. Yet it appears on the updated federal infrastructure funding list released by the minister today[16].

Is Infrastructure Australia independent enough to reject the Suburban Rail Loop if it fails its assessment criteria?

‘Not demonstrably merit-based’

The Suburban Rail Loop is not alone as an infrastructure project promoted well in advance of its assessment. In the leadup to the 2019 election, the Morrison government released proposals for car parks at suburban rail stations.

This scheme was never submitted to Infrastructure Australia and was later found by the Commonwealth Auditor General to be “not demonstrably merit-based[17]”, a finding Labor categorised as “sports rorts on steroids[18]”.

Cover of Independent Review
Department of Infrastructure, Transport and Regional Development[19] The Independent Strategic Review of the national infrastructure program released on Thursday responds in part to these concerns. It recommends that 86 projects deemed of lower merit be stopped, and supports another 156, with 32 to be determined through further assessment. The review also offers advice[20] about how to improve infrastructure planning. It recommends each state prepare an annual infrastructure plan identifying priority projects over ten years, and their proposed sequencing. The federal government would provide an annual overview of infrastructure planning and priorities to inform assessment and decisions. Funding would usually be split 50:50 between the federal government and the states. These are useful improvements but they still leave infrastructure open to gaming. There’s more that could be done. The beginning of a way forward A first option would be to raise the value threshold for individual projects the Commonwealth should even begin to consider, say $1 billion. Others could be funded through a bulk annual grant to each state. A second option would be to require a higher merit threshold for considering a project. This would involve assessing regulatory, pricing or taxation alternatives before considering an infrastructure solution. If after this assessment, infrastructure is deemed appropriate, alternative types of projects should be openly considered. Only after that’s done should the preferred project be considered for funding. If this had applied to the Suburban Rail Loop, the Victorian government could have been told to assess other options, such as the tram and bus[21] put forward by researchers at the University of Melbourne. Read more: Transurban's West Gate tollway is a road into uncharted territory[22] For projects worth more than $1 billion, open parliamentary inquiries could be held to transparently assess their merits and allow for expert and public opinion to be aired on the record. A further option would be to require rigorous carbon emission analysis of all projects and reject those that conflict with national climate goals. This would make big infrastructure less attractive, given the carbon content of concrete and steel, and in transport would favour rail freight over roads, and public transport, walking and cycling over driving. Lastly, all projects funded through Infrastructure Australia should be subject to independent public after-the-event analysis to create an accessible database of what worked and what did not. Infrastructure is costly. Cheap politics and getting it wrong adds to inflation. References^ list (www.infrastructure.gov.au)^ independent strategic review (www.infrastructure.gov.au)^ $32.8 billion (theconversation.com)^ Infrastructure Australia (www.infrastructureaustralia.gov.au)^ Infrastructure review recommends culling 82 planned projects (theconversation.com)^ full up (www.afr.com)^ robodebt (theconversation.com)^ committed to the project (www.abc.net.au)^ less than one (www.abc.net.au)^ high priority (www.infrastructureaustralia.gov.au)^ priority (www.infrastructureaustralia.gov.au)^ Julian Smith/AAP (photos.aap.com.au)^ abandoned (www.abc.net.au)^ Suburban Rail Loop (bigbuild.vic.gov.au)^ $2.2 billion (www.theage.com.au)^ released by the minister today (www.infrastructure.gov.au)^ not demonstrably merit-based (www.anao.gov.au)^ sports rorts on steroids (www.theguardian.com)^ Department of Infrastructure, Transport and Regional Development (www.infrastructure.gov.au)^ advice (www.infrastructure.gov.au)^ tram and bus (apo.org.au)^ Transurban's West Gate tollway is a road into uncharted territory (theconversation.com)

Read more https://theconversation.com/the-government-just-killed-50-infrastructure-projects-what-matters-is-whether-it-will-fund-them-on-merit-from-now-on-217900

Times Magazine

Headless CMS in Digital Twins and 3D Product Experiences

Image by freepik As the metaverse becomes more advanced and accessible, it's clear that multiple sectors will use digital twins and 3D product experiences to visualize, connect, and streamline efforts better. A digital twin is a virtual replica of ...

The Decline of Hyper-Casual: How Mid-Core Mobile Games Took Over in 2025

In recent years, the mobile gaming landscape has undergone a significant transformation, with mid-core mobile games emerging as the dominant force in app stores by 2025. This shift is underpinned by changing user habits and evolving monetization tr...

Understanding ITIL 4 and PRINCE2 Project Management Synergy

Key Highlights ITIL 4 focuses on IT service management, emphasising continual improvement and value creation through modern digital transformation approaches. PRINCE2 project management supports systematic planning and execution of projects wit...

What AI Adoption Means for the Future of Workplace Risk Management

Image by freepik As industrial operations become more complex and fast-paced, the risks faced by workers and employers alike continue to grow. Traditional safety models—reliant on manual oversight, reactive investigations, and standardised checklist...

From Beach Bops to Alpine Anthems: Your Sonos Survival Guide for a Long Weekend Escape

Alright, fellow adventurers and relaxation enthusiasts! So, you've packed your bags, charged your devices, and mentally prepared for that glorious King's Birthday long weekend. But hold on, are you really ready? Because a true long weekend warrior kn...

Effective Commercial Pest Control Solutions for a Safer Workplace

Keeping a workplace clean, safe, and free from pests is essential for maintaining productivity, protecting employee health, and upholding a company's reputation. Pests pose health risks, can cause structural damage, and can lead to serious legal an...

The Times Features

Exploring the Curriculum at a Modern Junior School in Melbourne

Key Highlights The curriculum at junior schools emphasises whole-person development, catering to children’s physical, emotional, and intellectual needs. It ensures early year...

Distressed by all the bad news? Here’s how to stay informed but still look after yourself

If you’re feeling like the news is particularly bad at the moment, you’re not alone. But many of us can’t look away – and don’t want to. Engaging with news can help us make ...

The Role of Your GP in Creating a Chronic Disease Management Plan That Works

Living with a long-term condition, whether that is diabetes, asthma, arthritis or heart disease, means making hundreds of small decisions every day. You plan your diet against m...

Troubleshooting Flickering Lights: A Comprehensive Guide for Homeowners

Image by rawpixel.com on Freepik Effectively addressing flickering lights in your home is more than just a matter of convenience; it's a pivotal aspect of both home safety and en...

My shins hurt after running. Could it be shin splints?

If you’ve started running for the first time, started again after a break, or your workout is more intense, you might have felt it. A dull, nagging ache down your shins after...

Metal Roof Replacement Cost Per Square Metre in 2025: A Comprehensive Guide for Australian Homeowners

In recent years, the trend of installing metal roofs has surged across Australia. With their reputation for being both robust and visually appealing, it's easy to understand thei...