The government just killed 50 infrastructure projects – what matters is whether it will fund them on merit from now on

  • Written by Jago Dodson, Professor of Urban Policy and Director, Centre for Urban Research, RMIT University
The government just killed 50 infrastructure projects – what matters is whether it will fund them on merit from now on

The federal government has just announced a list[1] of projects to be abandoned as a result of an independent strategic review[2] of its infrastructure investment program.

The review found the cost of the A$120 billion, ten-year program had blown out by $32.8 billion[3], half of which was in projects not yet under construction.

But the flaws in national infrastructure planning go much deeper than the question of whether or how projects are listed on a spreadsheet, and how much their costs blow out.

A national framework built around Infrastructure Australia[4] was supposed to resolve differences between the states and the federal government on projects before they get approved.

Read more: Infrastructure review recommends culling 82 planned projects[5]

In the late 1990s and early 2000s, as Australia was recovering from recession, demands for new infrastructure funding grew.

Sydney, which had been “full up[6]” according to then NSW Premier Bob Carr and had economised on spending in the runup to the 2000 Olympics, desperately needed new infrastructure.

With their budgets constrained, states began pitching projects to the federal government, but incoherently and without a national framework.

The Rudd Labor government went to the 2007 election promising to bring coherence and rationality to national infrastructure planning.

Independent advice was meant to fix things…

Rudd and the then infrastructure minister Anthony Albanese established Infrastructure Australia as an independent statutory authority to provide advice on national needs and project priorities. The idea of it being independent came from technocratic bodies such as the Reserve Bank and the Productivity Commission.

Infastructure Australia was diligent in its approach.

It undertook national infrastructure audits to determine key areas of need, prepared uniform criteria by which projects should be assessed, and compiled priority lists of projects assessed on merit against those criteria.

Final decisions on funding would rest with ministers, but they would have the benefit of Infrastructure Australia’s independent advice.

…but big projects are inherently political

But large infrastructure projects addressing public and business needs are unavoidably political.

As desirable as an independent body assessing projects on merit seems, retail politics militate strongly against delegating decisions to technocratic bodies.

But conversely, a minister who is seen to reject official independent advice is politically exposed. This gives both the agency and the minister strong imperatives to preserve each other’s modesty.

From the mid-2010s to the early 2020s, the Australian public service became increasingly politicised, resulting in hollowing out of expertise, loss of independence, and scandals such as robodebt[7].

‘High priority’ versus mere ‘priority’

Infrastructure Australia, while independent of the core public service in the same way as is the Reserve Bank, became subject to political pressure.

This is exemplified by the case of Victoria’s East-West Link toll road. The Abbott Commonwealth government committed to the project[8] ahead of the 2014 Victorian election, despite the project having a benefit-cost ratio of less than one[9], meaning that its benefits were less than its costs.

Under the pressure to resolve the contradiction, Infrastructure Australia created a “high priority[10]” list in addition to its existing “priority[11]” list.

The new “high priority” list would include only the projects assessed as having the greatest value to the nation. The existing repurposed “priority” list could house the politically important but less meritorious projects, allowing politicians to claim these projects were “priorities”, even if their absolute merit was doubtful.

East-West Link funded then cancelled

East West Link: unpopular and found not to be worth the cost. Julian Smith/AAP[12]

The 2014 Victorian election result rescued some modesty after the newly elected Dan Andrews abandoned[13] the East-West Link, but the interplay between political needs and technical rationality has if anything gotten worse.

Andrews’s $200 billion Suburban Rail Loop[14] was endorsed electorally at the 2018 and 2022 state elections despite not appearing in any formal metropolitan or statutory transport plans.

At the time of the 2022 federal election, it hadn’t been submitted to Infrastructure Australia for assessment. But the federal Labor opposition, now the government, committed $2.2 billion[15] to it.

Victoria has since submitted the Suburban Rail Loop to Infrastructure Australia, but the assessment is unfinished. Yet it appears on the updated federal infrastructure funding list released by the minister today[16].

Is Infrastructure Australia independent enough to reject the Suburban Rail Loop if it fails its assessment criteria?

‘Not demonstrably merit-based’

The Suburban Rail Loop is not alone as an infrastructure project promoted well in advance of its assessment. In the leadup to the 2019 election, the Morrison government released proposals for car parks at suburban rail stations.

This scheme was never submitted to Infrastructure Australia and was later found by the Commonwealth Auditor General to be “not demonstrably merit-based[17]”, a finding Labor categorised as “sports rorts on steroids[18]”.

Cover of Independent Review
Department of Infrastructure, Transport and Regional Development[19] The Independent Strategic Review of the national infrastructure program released on Thursday responds in part to these concerns. It recommends that 86 projects deemed of lower merit be stopped, and supports another 156, with 32 to be determined through further assessment. The review also offers advice[20] about how to improve infrastructure planning. It recommends each state prepare an annual infrastructure plan identifying priority projects over ten years, and their proposed sequencing. The federal government would provide an annual overview of infrastructure planning and priorities to inform assessment and decisions. Funding would usually be split 50:50 between the federal government and the states. These are useful improvements but they still leave infrastructure open to gaming. There’s more that could be done. The beginning of a way forward A first option would be to raise the value threshold for individual projects the Commonwealth should even begin to consider, say $1 billion. Others could be funded through a bulk annual grant to each state. A second option would be to require a higher merit threshold for considering a project. This would involve assessing regulatory, pricing or taxation alternatives before considering an infrastructure solution. If after this assessment, infrastructure is deemed appropriate, alternative types of projects should be openly considered. Only after that’s done should the preferred project be considered for funding. If this had applied to the Suburban Rail Loop, the Victorian government could have been told to assess other options, such as the tram and bus[21] put forward by researchers at the University of Melbourne. Read more: Transurban's West Gate tollway is a road into uncharted territory[22] For projects worth more than $1 billion, open parliamentary inquiries could be held to transparently assess their merits and allow for expert and public opinion to be aired on the record. A further option would be to require rigorous carbon emission analysis of all projects and reject those that conflict with national climate goals. This would make big infrastructure less attractive, given the carbon content of concrete and steel, and in transport would favour rail freight over roads, and public transport, walking and cycling over driving. Lastly, all projects funded through Infrastructure Australia should be subject to independent public after-the-event analysis to create an accessible database of what worked and what did not. Infrastructure is costly. Cheap politics and getting it wrong adds to inflation. References^ list (www.infrastructure.gov.au)^ independent strategic review (www.infrastructure.gov.au)^ $32.8 billion (theconversation.com)^ Infrastructure Australia (www.infrastructureaustralia.gov.au)^ Infrastructure review recommends culling 82 planned projects (theconversation.com)^ full up (www.afr.com)^ robodebt (theconversation.com)^ committed to the project (www.abc.net.au)^ less than one (www.abc.net.au)^ high priority (www.infrastructureaustralia.gov.au)^ priority (www.infrastructureaustralia.gov.au)^ Julian Smith/AAP (photos.aap.com.au)^ abandoned (www.abc.net.au)^ Suburban Rail Loop (bigbuild.vic.gov.au)^ $2.2 billion (www.theage.com.au)^ released by the minister today (www.infrastructure.gov.au)^ not demonstrably merit-based (www.anao.gov.au)^ sports rorts on steroids (www.theguardian.com)^ Department of Infrastructure, Transport and Regional Development (www.infrastructure.gov.au)^ advice (www.infrastructure.gov.au)^ tram and bus (apo.org.au)^ Transurban's West Gate tollway is a road into uncharted territory (theconversation.com)

Read more https://theconversation.com/the-government-just-killed-50-infrastructure-projects-what-matters-is-whether-it-will-fund-them-on-merit-from-now-on-217900

The Times Features

Will the Wage Price Index growth ease financial pressure for households?

The Wage Price Index’s quarterly increase of 0.8% has been met with mixed reactions. While Australian wages continue to increase, it was the smallest increase in two and a half...

Back-to-School Worries? 70% of Parents Fear Their Kids Aren’t Ready for Day On

Australian parents find themselves confronting a key decision: should they hold back their child on the age border for another year before starting school? Recent research from...

Democratising Property Investment: How MezFi is Opening Doors for Everyday Retail Investors

The launch of MezFi today [Friday 15th November] marks a watershed moment in Australian investment history – not just because we're introducing something entirely new, but becaus...

Game of Influence: How Cricket is Losing Its Global Credibility

be losing its credibility on the global stage. As other sports continue to capture global audiences and inspire unity, cricket finds itself increasingly embroiled in political ...

Amazon Australia and DoorDash announce two-year DashPass offer only for Prime members

New and existing Prime members in Australia can enjoy a two-year membership to DashPass for free, and gain access to AU$0 delivery fees on eligible DoorDash orders New offer co...

6 things to do if your child’s weight is beyond the ideal range – and 1 thing to avoid

One of the more significant challenges we face as parents is making sure our kids are growing at a healthy rate. To manage this, we take them for regular check-ups with our GP...

Times Magazine

If You Want To Purchase a Property In Melbourne – Engage With An Owner’s Corporation

Many Australians are looking to get on the property ladder this year because they know and understand that property continues to go up in price year-on-year and so do rental opportunities. If this describes you then it’s likely that you still wan...

Essential Tips for Selecting the Best Bike Racks for Your Needs

Bike racks for surfers have grown in popularity in recent years, catering to the special needs of this niche industry. Surfers can use these racks to transport their boards to and from the beach without needing a larger vehicle or the inconvenience...

Understanding How a Solar Inverter Works in a Residential Solar System

As the world shifts towards sustainable energy sources, residential solar systems have become increasingly popular. At the heart of these systems is a critical component known as the solar inverter. Understanding how a solar inverter works is ess...

BLUETTI EB3A Portable Power Station review

At work and on assignment The crew at TheTimes.com.au were offered the opportunity to carry out a long term test of a BLUETTI power station. When the EB3A power station arrived by courier, we unpacked it with enthusiasm and some curiosity as none o...

Elevate Your Off-Road Experience with Ozzytyres’ 4x4 Wheel and Tyre Packages

The right wheel and tyre package can make all the difference between a thrilling adventure and a frustrating experience. An extensive range of high-quality 4x4 wheel and tyre packages from Ozzytyres can help you. They are designed to elevate your v...

NRMA to introduce payment for EV charging

NRMA will commence a payment system for the use of its fast charging network from this week and then rolled out over the coming months to eventually include all 100 charging stations. A cost structure will commence at NRMA’s Sydney Olympic Par...