Australia needs tradies and materials to build the power grid of the future. So where are they?

  • Written by Chris Briggs, Research Director, Institute for Sustainable Futures, University of Technology Sydney

As Australia’s electricity supply shifts to clean energy, a big challenge is looming. How do we “keep the lights on” as big coal plants close, and a far-flung network of wind and solar generators replaces them?

This balancing act was outlined in the latest annual stocktake[1] by the Australian Energy Market Operator. It said[2] large-scale renewables projects must be delivered on time and in full[3] if electricity in Australia’s eastern mainland states, plus South Australia and Tasmania, was to remain stable in the next decade.

The energy transition doesn’t just mean building wind and solar generators. It also means getting electricity to where consumers need it, via the transmission network.

But Australia desperately needs the skilled workers and materials to build that infrastructure and keep the energy transition on track.

wind turbine and fence at sunset
How do we keep the lights on as renewables replace big coal plants? James Ross/AAP

The transmission crunch

After electricity is generated by a coal plant or wind farm, it must be transported to an electrical substation. There, the electricity is converted to a lower voltage, then sent to homes and businesses.

Moving electricity from the generator to the substation requires high-voltage cables, towers to support them, and devices known as “transformers” to convert the energy. Collectively, this is known as the transmission network[4].

The clean energy transition is testing Australia’s transmission capabilities. Solar and wind farms are often built in regional areas, where it’s sunny and windy. In many cases, transmission infrastructure to those areas doesn’t exist, or needs upgrading.

The Albanese government’s A$20 billion Rewiring the Nation[5] policy is an attempt to grapple with this problem. It aims to help finance the 10,000 kilometres[6] of transmission lines the Australian Energy Market Operator has identified as needed.

But transmission lines are large, complex projects that take years to plan and build. Projects often suffer delays, both in Australia[7] and around the world.

The International Energy Agency estimates 80 million kilometres of power lines[8] must be built or refurbished globally by 2040 – and projects are not keeping pace.

Several factors can delay the rollout of the transmission network. Opposition[9] from communities or landholders to hosting infrastructure is a well-publicised problem.

But two other hurdles are often overlooked: the equipment and workers needed for the massive expansion.

electrical tower
Electricity transmission infrastructure is expensive and complex to upgrade and build. Shutterstock[10]

How to build an electricity grid

Building transmission lines involves:

  • civil works to install foundations and erect the towers

  • electrical works to string the lines between the towers with cranes or helicopters[11] and connect to the grid

  • installing sub-stations and transformers.

Most materials are imported. Specialised components such as lines, transformers and cables are manufactured near bigger markets[12] in Europe and the United States. Transmission towers are imported from overseas and assembled in Australia.

And workers are needed to put all the materials together. They include construction managers, electrical engineers, electricians, truck drivers, construction riggers and earthmoving operators.

The Australian Energy Market Operator now factors in a 12-month delay for transmission projects, based on recent precedent. It also notes many are scheduled for completion between 2025 and 2030.

This will create a spike in demand for equipment and workers.

transmission tower and lines in green landscape
Transmission lines carry electricity over vast distances. Shutterstock[13]

The race for materials and workers

Around the world, transmission projects have been hit by delays in recent years. Specialised components[14] must be ordered well in advance, increasing lead times for projects.

And Australia is a small buyer located a long way from manufacturers. Larger, established buyers are often prioritised, leaving Australia struggling to compete[15].

The workforce required for transmission projects is not especially large – peaking at around 4,000 workers[16] in the late 2020s.

However, there is a shortage of specialised labour. Australia has been importing skilled transmission workers[17]. But as transmission projects scale up globally, this labour pool may dry up.

As one project manager noted in a federal government report in 2021[18], the transmission industry is bracing for worker shortages if multiple projects proceed at the same time:

We don’t have enough substation specialists, commissioning specialists or linesworkers across Australia. […] It’s going to be tricky.

Some workers can be sourced from other industries. But they must be trained or upskilled, and tradespeople may not want to move to regional areas or become fly in-fly out (FIFO) workers. As a transmission builder noted in the report:

if someone has a choice between a FIFO or to live in Sydney or Brisbane and work on overhead rail then what do you choose – jumping on a plane and living in a camp to do a 12-hour day?

And what about electricians? Australia faces a shortage of sparkies as renewable energy projects scale up and homes move away from gas towards electrification. Jobs Skills Australia estimates the transition to a clean energy economy will require between 26,000 and 42,000 electricians[19] out to 2030.

gloved hands tinker with power box
Australia already has a shortage of electricians. Shutterstock[20]

Smoothing the bumps

Securing the materials we need to build out the grid will be difficult.

Companies have begun “bundling up” orders[21] for several transmission projects at once, to increase their buying power with overseas manufacturers. Proposals for local manufacturing[22] of components exist, but these take time and could only reduce, not eliminate, our dependence on imports.

National coordination is needed to smooth the peaks in demand – for both materials and workers – created by many simultaneous transmission projects.

On the labour front, a huge training effort is needed, especially for engineers and key trades. Some initiatives are underway[23], but not at the scale required.

Unless governments and industry tackle these problems more seriously, Australia’s clean energy transition could face major delays.

References

  1. ^ annual stocktake (theconversation.com)
  2. ^ said (aemo.com.au)
  3. ^ on time and in full (theconversation.com)
  4. ^ transmission network (theconversation.com)
  5. ^ Rewiring the Nation (www.dcceew.gov.au)
  6. ^ finance the 10,000 kilometres (aemo.com.au)
  7. ^ Australia (nexaadvisory.com.au)
  8. ^ 80 million kilometres of power lines (www.iea.org)
  9. ^ Opposition (theconversation.com)
  10. ^ Shutterstock (www.shutterstock.com)
  11. ^ helicopters (www.youtube.com)
  12. ^ manufactured near bigger markets (iea.blob.core.windows.net)
  13. ^ Shutterstock (www.shutterstock.com)
  14. ^ Specialised components (www.iea.org)
  15. ^ struggling to compete (www.ey.com)
  16. ^ 4,000 workers (www.uts.edu.au)
  17. ^ skilled transmission workers (www.infrastructureaustralia.gov.au)
  18. ^ federal government report in 2021 (www.infrastructureaustralia.gov.au)
  19. ^ 26,000 and 42,000 electricians (www.jobsandskills.gov.au)
  20. ^ Shutterstock (www.shutterstock.com)
  21. ^ have begun “bundling up” orders (www.energynetworks.com.au)
  22. ^ local manufacturing (www.manmonthly.com.au)
  23. ^ initiatives are underway (www.thomsonbridge.com)

Read more https://theconversation.com/australia-needs-tradies-and-materials-to-build-the-power-grid-of-the-future-so-where-are-they-237858

Active Wear

Times Magazine

Myer celebrates 70 years of Christmas windows magic with the LEGO Group

To mark the 70th anniversary of the Myer Christmas Windows, Australia’s favourite department store...

Kindness Tops the List: New Survey Reveals Australia’s Defining Value

Commentary from Kath Koschel, founder of Kindness Factory.  In a time where headlines are dominat...

In 2024, the climate crisis worsened in all ways. But we can still limit warming with bold action

Climate change has been on the world’s radar for decades[1]. Predictions made by scientists at...

End-of-Life Planning: Why Talking About Death With Family Makes Funeral Planning Easier

I spend a lot of time talking about death. Not in a morbid, gloomy way—but in the same way we d...

YepAI Joins Victoria's AI Trade Mission to Singapore for Big Data & AI World Asia 2025

YepAI, a Melbourne-based leader in enterprise artificial intelligence solutions, announced today...

Building a Strong Online Presence with Katoomba Web Design

Katoomba web design is more than just creating a website that looks good—it’s about building an onli...

The Times Features

Myer celebrates 70 years of Christmas windows magic with the LEGO Group

To mark the 70th anniversary of the Myer Christmas Windows, Australia’s favourite department store...

Pharmac wants to trim its controversial medicines waiting list – no list at all might be better

New Zealand’s drug-buying agency Pharmac is currently consulting[1] on a change to how it mana...

NRMA Partnership Unlocks Cinema and Hotel Discounts

My NRMA Rewards, one of Australia’s largest membership and benefits programs, has announced a ne...

Restaurants to visit in St Kilda and South Yarra

Here are six highly-recommended restaurants split between the seaside suburb of St Kilda and the...

The Year of Actually Doing It

There’s something about the week between Christmas and New Year’s that makes us all pause and re...

Jetstar to start flying Sunshine Coast to Singapore Via Bali With Prices Starting At $199

The Sunshine Coast is set to make history, with Jetstar today announcing the launch of direct fl...

Why Melbourne Families Are Choosing Custom Home Builders Over Volume Builders

Across Melbourne’s growing suburbs, families are re-evaluating how they build their dream homes...

Australian Startup Business Operators Should Make Connections with Asian Enterprises — That Is Where Their Future Lies

In the rapidly shifting global economy, Australian startups are increasingly finding that their ...

How early is too early’ for Hot Cross Buns to hit supermarket and bakery shelves

Every year, Australians find themselves in the middle of the nation’s most delicious dilemmas - ...