Australia needs tradies and materials to build the power grid of the future. So where are they?

  • Written by Chris Briggs, Research Director, Institute for Sustainable Futures, University of Technology Sydney

As Australia’s electricity supply shifts to clean energy, a big challenge is looming. How do we “keep the lights on” as big coal plants close, and a far-flung network of wind and solar generators replaces them?

This balancing act was outlined in the latest annual stocktake[1] by the Australian Energy Market Operator. It said[2] large-scale renewables projects must be delivered on time and in full[3] if electricity in Australia’s eastern mainland states, plus South Australia and Tasmania, was to remain stable in the next decade.

The energy transition doesn’t just mean building wind and solar generators. It also means getting electricity to where consumers need it, via the transmission network.

But Australia desperately needs the skilled workers and materials to build that infrastructure and keep the energy transition on track.

wind turbine and fence at sunset
How do we keep the lights on as renewables replace big coal plants? James Ross/AAP

The transmission crunch

After electricity is generated by a coal plant or wind farm, it must be transported to an electrical substation. There, the electricity is converted to a lower voltage, then sent to homes and businesses.

Moving electricity from the generator to the substation requires high-voltage cables, towers to support them, and devices known as “transformers” to convert the energy. Collectively, this is known as the transmission network[4].

The clean energy transition is testing Australia’s transmission capabilities. Solar and wind farms are often built in regional areas, where it’s sunny and windy. In many cases, transmission infrastructure to those areas doesn’t exist, or needs upgrading.

The Albanese government’s A$20 billion Rewiring the Nation[5] policy is an attempt to grapple with this problem. It aims to help finance the 10,000 kilometres[6] of transmission lines the Australian Energy Market Operator has identified as needed.

But transmission lines are large, complex projects that take years to plan and build. Projects often suffer delays, both in Australia[7] and around the world.

The International Energy Agency estimates 80 million kilometres of power lines[8] must be built or refurbished globally by 2040 – and projects are not keeping pace.

Several factors can delay the rollout of the transmission network. Opposition[9] from communities or landholders to hosting infrastructure is a well-publicised problem.

But two other hurdles are often overlooked: the equipment and workers needed for the massive expansion.

electrical tower
Electricity transmission infrastructure is expensive and complex to upgrade and build. Shutterstock[10]

How to build an electricity grid

Building transmission lines involves:

  • civil works to install foundations and erect the towers

  • electrical works to string the lines between the towers with cranes or helicopters[11] and connect to the grid

  • installing sub-stations and transformers.

Most materials are imported. Specialised components such as lines, transformers and cables are manufactured near bigger markets[12] in Europe and the United States. Transmission towers are imported from overseas and assembled in Australia.

And workers are needed to put all the materials together. They include construction managers, electrical engineers, electricians, truck drivers, construction riggers and earthmoving operators.

The Australian Energy Market Operator now factors in a 12-month delay for transmission projects, based on recent precedent. It also notes many are scheduled for completion between 2025 and 2030.

This will create a spike in demand for equipment and workers.

transmission tower and lines in green landscape
Transmission lines carry electricity over vast distances. Shutterstock[13]

The race for materials and workers

Around the world, transmission projects have been hit by delays in recent years. Specialised components[14] must be ordered well in advance, increasing lead times for projects.

And Australia is a small buyer located a long way from manufacturers. Larger, established buyers are often prioritised, leaving Australia struggling to compete[15].

The workforce required for transmission projects is not especially large – peaking at around 4,000 workers[16] in the late 2020s.

However, there is a shortage of specialised labour. Australia has been importing skilled transmission workers[17]. But as transmission projects scale up globally, this labour pool may dry up.

As one project manager noted in a federal government report in 2021[18], the transmission industry is bracing for worker shortages if multiple projects proceed at the same time:

We don’t have enough substation specialists, commissioning specialists or linesworkers across Australia. […] It’s going to be tricky.

Some workers can be sourced from other industries. But they must be trained or upskilled, and tradespeople may not want to move to regional areas or become fly in-fly out (FIFO) workers. As a transmission builder noted in the report:

if someone has a choice between a FIFO or to live in Sydney or Brisbane and work on overhead rail then what do you choose – jumping on a plane and living in a camp to do a 12-hour day?

And what about electricians? Australia faces a shortage of sparkies as renewable energy projects scale up and homes move away from gas towards electrification. Jobs Skills Australia estimates the transition to a clean energy economy will require between 26,000 and 42,000 electricians[19] out to 2030.

gloved hands tinker with power box
Australia already has a shortage of electricians. Shutterstock[20]

Smoothing the bumps

Securing the materials we need to build out the grid will be difficult.

Companies have begun “bundling up” orders[21] for several transmission projects at once, to increase their buying power with overseas manufacturers. Proposals for local manufacturing[22] of components exist, but these take time and could only reduce, not eliminate, our dependence on imports.

National coordination is needed to smooth the peaks in demand – for both materials and workers – created by many simultaneous transmission projects.

On the labour front, a huge training effort is needed, especially for engineers and key trades. Some initiatives are underway[23], but not at the scale required.

Unless governments and industry tackle these problems more seriously, Australia’s clean energy transition could face major delays.

References

  1. ^ annual stocktake (theconversation.com)
  2. ^ said (aemo.com.au)
  3. ^ on time and in full (theconversation.com)
  4. ^ transmission network (theconversation.com)
  5. ^ Rewiring the Nation (www.dcceew.gov.au)
  6. ^ finance the 10,000 kilometres (aemo.com.au)
  7. ^ Australia (nexaadvisory.com.au)
  8. ^ 80 million kilometres of power lines (www.iea.org)
  9. ^ Opposition (theconversation.com)
  10. ^ Shutterstock (www.shutterstock.com)
  11. ^ helicopters (www.youtube.com)
  12. ^ manufactured near bigger markets (iea.blob.core.windows.net)
  13. ^ Shutterstock (www.shutterstock.com)
  14. ^ Specialised components (www.iea.org)
  15. ^ struggling to compete (www.ey.com)
  16. ^ 4,000 workers (www.uts.edu.au)
  17. ^ skilled transmission workers (www.infrastructureaustralia.gov.au)
  18. ^ federal government report in 2021 (www.infrastructureaustralia.gov.au)
  19. ^ 26,000 and 42,000 electricians (www.jobsandskills.gov.au)
  20. ^ Shutterstock (www.shutterstock.com)
  21. ^ have begun “bundling up” orders (www.energynetworks.com.au)
  22. ^ local manufacturing (www.manmonthly.com.au)
  23. ^ initiatives are underway (www.thomsonbridge.com)

Read more https://theconversation.com/australia-needs-tradies-and-materials-to-build-the-power-grid-of-the-future-so-where-are-they-237858

The Times Features

What’s the difference between wholemeal and wholegrain bread? Not a whole lot

If you head to the shops to buy bread, you’ll face a variety of different options. But it can be hard to work out the difference between all the types on sale. For instance...

Expert Tips for Planning Home Electrical Upgrades in Australia

Home electrical systems in Australia are quite intricate and require careful handling. Safety and efficiency determine the functionality of these systems, and it's critical to ...

Floor Tiling: Choosing the Right Tiles for Every Room

Choosing floor tiles is more than just grabbing the first design that catches your eye at the showroom. You need to think about how the floor tiling option will fit into your spa...

Exploring Family Caravans: Your Ultimate Guide to Mobile Living and Travel

Australia is the land of vast horizons, spectacular coastlines, and a never-ending adventure. As landscapes and adventures vary across the country, Voyager will route you, carava...

Energy-Efficient Homes in Geelong: How a Local Electrician Can Help You Save Money

Rising energy bills don’t have to be the new normal. With Victoria’s energy prices up 25% last year, Geelong homeowners are fighting back and winning, by partnering with licenced...

Eating disorders don’t just affect teen girls. The risk may go up around pregnancy and menopause too

Eating disorders impact more than 1.1 million people in Australia[1], representing 4.5% of the population. These disorders include binge eating disorder, bulimia nervosa, and...

Times Magazine

The Power of Digital Signage in Modern Marketing

In a fast-paced digital world, businesses must find innovative ways to capture consumer attention. Digital signage has emerged as a powerful solution, offering dynamic and engaging content that attracts and retains customers. From retail stores to ...

Why Cloud Computing Is the Future of IT Infrastructure for Enterprises

Globally, cloud computing is changing the way business organizations manage their IT infrastructure. It offers cheap, flexible and scalable solutions. Cloud technologies are applied in organizations to facilitate procedures and optimize operation...

First Nations Writers Festival

The First Nations Writers Festival (FNWF) is back for its highly anticipated 2025 edition, continuing its mission to celebrate the voices, cultures and traditions of First Nations communities through literature, art and storytelling. Set to take ...

Improving Website Performance with a Cloud VPS

Websites represent the new mantra of success. One slow website may make escape for visitors along with income too. Therefore it's an extra offer to businesses seeking better performance with more scalability and, thus represents an added attracti...

Why You Should Choose Digital Printing for Your Next Project

In the rapidly evolving world of print media, digital printing has emerged as a cornerstone technology that revolutionises how businesses and creative professionals produce printed materials. Offering unparalleled flexibility, speed, and quality, d...

What to Look for When Booking an Event Space in Melbourne

Define your event needs early to streamline venue selection and ensure a good fit. Choose a well-located, accessible venue with good transport links and parking. Check for key amenities such as catering, AV equipment, and flexible seating. Pla...

LayBy Shopping