Without a massive grid upgrade, the Coalition’s nuclear plan faces a high-voltage hurdle

  • Written by Asma Aziz, Senior Lecturer in Power Engineering, Edith Cowan University
Without a massive grid upgrade, the Coalition’s nuclear plan faces a high-voltage hurdle

Keeping the lights on in Australia is a complex task. Enough capacity must be ensured everywhere in the country, at every moment. Surplus in one location won’t solve shortages in another, unless we have the transmission infrastructure to transmit electricity between them.

The transmission network largely consists of high-voltage lines and towers, as well as transformers which transfer electrical energy from one circuit to another.

Australia’s transmission network is one of the oldest and longest in the world. As coal stations close and more renewable energy is built, the task of upgrading the system becomes even more pressing. So formidable is the challenge, it’s one of the biggest roadblocks Australia faces in reaching its crucial goal of net-zero emissions by 2050.

The Coalition’s plan for seven nuclear energy plants[1] in Australia further complicates the task. A clear policy direction for Australia’s electricity system is urgently needed.

headshot of man talking
The Coalition’s nuclear plan complicates Australia’s energy transition. Lukas Coch

Lots of work to do

In technical terms, transmission congestion occurs when an element on the network, such as a high-voltage power line or transformer, reaches capacity and cannot carry more electricity.

Think of it as like traffic in a city. During rush hour, bottlenecks occur when there are more vehicles than the roads can handle. During times of peak electricity demand, electricity lines and transformers can also reach their limits. Exceeding the limits of the network can damage equipment and lead to power outages.

Between now and 2050, Australia’s electricity consumption will surge[2]. We’ll need to draw power from increasingly diverse and far-flung sources. Coal power plants, typically located near large population centres, will close. Energy generation from solar and wind farms, usually located in regional and remote areas, will increase.

Importantly, we must make the distinction between electricity capacity and whether that electricity is “dispatchable”, or can be released on demand. That’s one reason why we need new transmission lines – to move electricity around the system as needed. The sooner we can build this capability, the quicker and cheaper our energy transition will be.

So far this decade, 490 kilometres of new transmission lines have reportedly been added[3] to the National Electricity Market, which serves the east coast and South Australia. A further 2,090 km of transmission lines are progressing from the planning phase to the construction phase.

There’s still a lot of work to do: around 10,000 km of new transmission lines is needed by 2050. Western Australia’s main electricity network also needs more than 4,000 km of new high-capacity transmission lines[4].

workers behind transmission lines
Australia needs 10,000 km of new transmission lines. Con Chronis/AAP

A looming problem

The network’s ability to carry electricity is influenced by several factors. They include weather conditions, patterns of electricity generation and demand, the capacity of individual elements such as transmission lines and transformers, and their reliability.

Congested transmission can cause fluctuations in power prices. If cheaper electricity cannot be transported to where it’s needed, more expensive generators are dispatched to meet demand. This increases the price[5] of electricity for both energy retailers and consumers. It can also lead to higher prices in some areas than others and poses financial risks for energy providers.

Transmission congestion in Australia is a looming problem. For example, South Australian transmission company ElectraNet forecasts[6] rising congestion on that state’s network due to planned expansions of electricity generators, peaking in the late 2020s and 2030s.

What’s more, planning studies have identified ageing assets in Queensland’s transmission network[7], requiring new routes to manage constraints and ensure reliable supply.

electricity bill and calculator
Power prices can fluctuate if electricity transmission networks are congested. Jono Searle/AAP

Where does nuclear fit in?

All this has implications for the Coalition’s nuclear plan, if it comes to fruition.

The CSIRO[8] and others[9] say a nuclear power plant of any size would not be operational in Australia until after 2040.

If transmission lines are congested at that future point, nuclear power plants may not be able to send all their electricity to the grid.

Nuclear plants are expensive to build and run. But they typically generate electricity continuously, helping to offset these costs. If the plants can’t feed into the grid, or can’t sell their electricity at competitive prices, they may lose revenue and struggle to cover their costs[10], affecting their long-term viability[11].

The continuous high output[12] of nuclear plants also helps them run efficiently[13]. Frequently adjusting energy output leads to more wear, lower efficiency and reduced energy production over time.

Constraining nuclear output can have broader repercussions, too. In France, for instance, nuclear output is at a 30-year low[14], forcing the country to import electricity and prepare for potential blackouts. The reactors are offline for maintenance, not due to transmission issues. But the example highlights the consequences when nuclear energy is taken out of the mix for any reason.

Clarity is needed

Finally, the increasing share of renewable energy in our electricity grid means there’s no guarantee transmission capacity will be available for nuclear energy.

As South Australia’s energy minister Tom Koutsantonis noted[15] on X, this poses challenges for the Coalition’s plan to build a nuclear plant at the site of an old coal station at Port Augusta and use existing transmission infrastructure:

The myth that a nuclear reactor could just plug into the old Pt Augusta coal power station transmission lines is not true. The transmission lines are already nearly full from new renewables. In truth, a nuclear reactor at Pt Augusta would need new transmission lines, the exact thing the LNP are complaining about.

So what’s the upshot of all this? Transmission infrastructure is a thorny policy problem, and divergent views among policymakers about energy policy only add to the challenges.

A clear direction on the future of Australia’s electricity grid, including transmission infrastructure, is essential. Without it, the energy transition will be slower and more expensive.

References

  1. ^ seven nuclear energy plants (theconversation.com)
  2. ^ will surge (aemo.com.au)
  3. ^ have reportedly been added (www.theguardian.com)
  4. ^ 4,000 km of new high-capacity transmission lines (www.wa.gov.au)
  5. ^ increases the price (www.aemc.gov.au)
  6. ^ forecasts (www.electranet.com.au)
  7. ^ Queensland’s transmission network (www.powerlink.com.au)
  8. ^ CSIRO (www.csiro.au)
  9. ^ others (blueprintinstitute.s3.ap-southeast-2.amazonaws.com)
  10. ^ struggle to cover their costs (thebulletin.org)
  11. ^ long-term viability (www.forbes.com)
  12. ^ continuous high output (www.iaea.org)
  13. ^ efficiently (www.energy.gov)
  14. ^ a 30-year low (www.reuters.com)
  15. ^ noted (x.com)

Read more https://theconversation.com/without-a-massive-grid-upgrade-the-coalitions-nuclear-plan-faces-a-high-voltage-hurdle-233458

The Times Features

Tassie’s best pie enters NSW with the launch National Pies’ new fresh range

Fresh from Tasmanian Bakeries in Hobart, National Pies has just delivered Tassie’s best-selling pie to the ready meals aisles of Woolworths stores across NSW.  The delicious roll o...

IORDANES SPYRIDON GOGOS RUNWAY | AFW 2025

Fifth Collection by ISG | Words + Photography by Cesar Ocampo Some runway shows are about the clothes. Others are about the culture they carry. With Iordanes Spyridon Gogos, it’s ...

AJE Resort ‘26 — “IMPRESSION”

Photographed by Cesar Ocampo | AFW 2025 Day 3, Barangaroo Pier Pavilion There are runways, and then there are moments. Aje’s Resort ‘26 collection, IMPRESSION, wasn’t just a fashi...

Miimi & Jiinda: Weaving Culture, Connection, and Country into Every Thread

By Cesar Ocampo When I sat down with Melissa Greenwood and her mother, Lauren Jarrett—founders of the First Nations brand Miimi & Jiinda—I knew this wasn’t going to be your st...

American Express to Provide $3.95M in Support for Restaurants Worldwide with 2025 “Backing Small” Grant Programs

Sydney, Australia 14 May 2025 – Applications are now open to small business owners who qualify for one  of American Express’ signature grant programs in 2025: Backing Internati...

FARAGE Summer '26 Brings Back the Power Suit — with Edge

Words & Photography by Cesar Ocampo On Day 2 of Australian Fashion Week, I stepped into the FARAGE Summer ’26 runway show not quite knowing what to expect—but walked away thin...

Times Magazine

Senior of the Year Nominations Open

The Allan Labor Government is encouraging all Victorians to recognise the valuable contributions of older members of our community by nominating them for the 2025 Victorian Senior of the Year Awards.  Minister for Ageing Ingrid Stitt today annou...

CNC Machining Meets Stage Design - Black Swan State Theatre Company & Tommotek

When artistry meets precision engineering, incredible things happen. That’s exactly what unfolded when Tommotek worked alongside the Black Swan State Theatre Company on several of their innovative stage productions. With tight deadlines and intrica...

Uniden Baby Video Monitor Review

Uniden has released another award-winning product as part of their ‘Baby Watch’ series. The BW4501 Baby Monitor is an easy to use camera for keeping eyes and ears on your little one. The camera is easy to set up and can be mounted to the wall or a...

Top Benefits of Hiring Commercial Electricians for Your Business

When it comes to business success, there are no two ways about it: qualified professionals are critical. While many specialists are needed, commercial electricians are among the most important to have on hand. They are directly involved in upholdin...

The Essential Guide to Transforming Office Spaces for Maximum Efficiency

Why Office Fitouts MatterA well-designed office can make all the difference in productivity, employee satisfaction, and client impressions. Businesses of all sizes are investing in updated office spaces to create environments that foster collaborat...

The A/B Testing Revolution: How AI Optimized Landing Pages Without Human Input

A/B testing was always integral to the web-based marketing world. Was there a button that converted better? Marketing could pit one against the other and see which option worked better. This was always through human observation, and over time, as d...

LayBy Shopping