I'm not an apologist for the Snowy 2.0 hydro scheme – but let's not obsess over the delays and cost blowouts

  • Written by Andrew Blakers, Professor of Engineering, Australian National University

The first power from the Snowy 2.0 pumped hydro project may not be delivered until 2028, it was revealed yesterday, triggering a fresh round of criticism over the controversial project.

The delay is undoubtedly inconvenient. But, despite speculation[1], the hold-up won’t noticeably slow the transition to renewable energy. The shift is driven by the compelling price advantage of solar and wind over coal and gas.

And in my view, we shouldn’t get too obsessed about exactly when Snowy 2.0 will be finished, or whether it costs more than first envisaged. In huge projects such as these, delays and cost blowouts are to be expected. And Snowy 2.0 offers us many lessons that will benefit subsequent pumped hydro projects.

I’m not an apologist for Snowy 2.0. I would have preferred it wasn’t built in a national park. But Australia’s renewable energy transformation will require a huge amount of energy storage – and the Snowy extension is an important part of the mix.

man in orange vest touches tunnel wall
Then prime minister Malcolm Turnbull visits Snowy Hydro in 2017. The Snowy 2.0 project is important for Australia’s energy shift. Alex Ellinghausen/AAP

A big deal for powering Australia

Federal government-owned Snowy Hydro on Wednesday said[2] Snowy 2.0 may not begin initial operation until the second half 2028 and may not be fully online until December 2029. It is also likely to suffer further cost blowouts beyond its current price tag of A$5.9 billion.

The project was originally costed at $2 billion and was expected to start operating in 2021.

In a statement[3], Snowy Hydro attributed the latest delay to COVID-19, global supply chain disruption, technical complications and geological issues.

Snowy 2.0 is the biggest energy storage project under construction in Australia. Pumped hydro storage involves[4] two small reservoirs spaced a few kilometres apart, one built 400-800 metres higher than the other, with tunnels connecting them.

On sunny and windy days, electricity is stored by pumping water up to the higher reservoir. Later, when energy is needed, the water is released downhill through the turbine to produce electricity. The same water goes up and down the hill for the life of the project.

The Albanese government has set a national target of 82% renewable electricity[5] by 2030 – most from solar and wind. These are intermittent energy sources, meaning they sometimes produce more energy than we need, and sometimes less. Energy storage helps smooth bumps in supply.

Solar and wind energy generation in the national electricity market meets about one-third of demand[6], up from 1% in 2009[7] and 9% in 2017[8]. So at the moment, we don’t need much energy storage because existing coal, gas and hydroelectric power stations still help balance electricity demand.

But by 2028, solar and wind are expected to generate about 60% of electricity in the market. By then, many more coal plants will have closed[9], and we’ll need other ways to balance supply and demand. That’s where Snowy 2.0 and other projects come in.

wind turbines on a hill
Energy storage helps smooth electricity supplies from solar and wind. Russell Freeman/AAP

A suite of options needed

So how do we make sure Australia’s electricity supplies remain reliable throughout the renewable energy transition? With a suite of technologies and projects.

The top priority is lots of new transmission infrastructure – mostly[10] high-voltage cables and associated towers, as well as transformers.

This infrastructure is needed to move power generated by new solar and wind projects in rural areas to the cities, and also between states.

Importantly, strong energy transmission between states hugely reduces the need for energy storage by smoothing out local weather. If it’s a wet, windless week in Victoria, electricity can be sent from New South Wales and South Australia. The following week, Victoria might return the favour.

Many other current and future options exist to balance out electricity supplies. They include:

  • off-river pumped hydro
  • grid-scale batteries
  • hot water storage tanks in homes and factories
  • high temperature thermal storage in factories to displace gas furnaces
  • activities to reduce electricity demand at peak times (known as demand management)
  • legacy gas turbines operating only occasionally
  • electric vehicle batteries.

The Snowy 2.0 delays mean other storage methods will take a stronger role in the interim.

Read more: What is the electricity transmission system, and why does it need fixing?[11]

large battery and wind turbines
Grid-scale batteries are part of the future energy mix. Red Havas

Pumped hydro vs the alternatives

Grid-scale batteries are useful for short-term energy storage – seconds, minutes and hours.

Several big battery projects are being deployed in Australia. This includes a project by German energy company RWE, which was just awarded[12] a major NSW government contract. It will generate 50 megawatts of power continuously for eight hours, and so has an energy storage capacity of 400 megawatt-hours.

But pumped hydro excels at[13] overnight and longer energy storage. Globally, pumped hydro constitutes about 95%[14] of electricity storage.

Australia has about 5,500 potential pumped hydro sites[15]. Since we only need ten or 20 pumped hydro systems, we can afford to be very choosy.

Australia has three operating pumped hydro energy storage systems. Two are under construction, including Snowy 2.0, and a dozen others are being planned[16] including big systems in Queensland[17] and Tasmania[18].

Pumped hydro uses water, whereas batteries use far more expensive electrochemicals. And hydro systems last much longer than big batteries. It’s not a question of choosing between batteries and pumped hydro. We need both.

Snowy 2.0 will have the capacity to generate 2,000 megawatts of continuous power for a whole week, and so will provide about 350,000 megawatt-hours of storage.

This is 40 times more power capacity than the 50 megawatt RWE battery, and about 900 times the energy storage.

The Pioneer-Burdekin[19] pumped hydro system being developed in Queensland will be able to generate 5,000 megawatts of power for 24 hours. This is 100 times more power and 300 times more energy storage than the RWE big battery.

What about the cost?

Upwards of $6 billion is not an insubstantial amount of money. But Snowy 2.0 would have been a bargain if it was completed for $2 billion. And even at, say, $9 billion, the project is still small compared to the $17 billion[20] Australia spends collectively each year on rooftop solar, windfarms, solar farms, electricity storage and powerlines.

The decision to locate Snowy 2.0 in a national park has been intensely criticised[21]. Indeed, my colleagues and I recently identified several attractive alternative sites for 500,000 megawatt-hour pumped hydro projects just a few kilometres west of Snowy 2.0, outside national parks, which you can see in this interactive map[22]. Each would require only a short tunnel and a single new reservoir.

However, at the time the Turnbull government committed to Snowy 2.0, it was the only large-scale storage option on the table. And it’s now fairly far down the construction track.

Read more: Snowy 2.0 threatens to pollute our rivers and wipe out native fish[23]

mountains, lake and mist
The decision to build the Snowy 2.0 project in a national park has been criticised. AAP

Snowy 2.0 is worth doing

Solar and wind could provide virtually all[24] future energy both in Australia and globally.

This would eliminate three-quarters[25] of Australia’s greenhouse emissions. But it requires a doubling of electricity generation, supported by up to one million megawatt-hours[26] of energy storage.

So for the sake of the renewables transition, let’s hope Snowy 2.0’s technical and financial difficulties are resolved.

Read more: Batteries of gravity and water: we found 1,500 new pumped hydro sites next to existing reservoirs[27]

References

  1. ^ speculation (www.smh.com.au)
  2. ^ said (www.snowyhydro.com.au)
  3. ^ statement (www.snowyhydro.com.au)
  4. ^ involves (theconversation.com)
  5. ^ 82% renewable electricity (www.aofm.gov.au)
  6. ^ about one-third of demand (opennem.org.au)
  7. ^ 1% in 2009 (opennem.org.au)
  8. ^ 9% in 2017 (opennem.org.au)
  9. ^ will have closed (theconversation.com)
  10. ^ mostly (theconversation.com)
  11. ^ What is the electricity transmission system, and why does it need fixing? (theconversation.com)
  12. ^ just awarded (reneweconomy.com.au)
  13. ^ excels at (www.aph.gov.au)
  14. ^ about 95% (sandia.gov)
  15. ^ 5,500 potential pumped hydro sites (theconversation.com)
  16. ^ are being planned (energycentral.com)
  17. ^ Queensland (qldhydro.com.au)
  18. ^ Tasmania (energycentral.com)
  19. ^ Pioneer-Burdekin (qldhydro.com.au)
  20. ^ $17 billion (www.abs.gov.au)
  21. ^ criticised (theconversation.com)
  22. ^ interactive map (re100.anu.edu.au)
  23. ^ Snowy 2.0 threatens to pollute our rivers and wipe out native fish (theconversation.com)
  24. ^ virtually all (theconversation.com)
  25. ^ eliminate three-quarters (www.sciencedirect.com)
  26. ^ one million megawatt-hours (www.sciencedirect.com)
  27. ^ Batteries of gravity and water: we found 1,500 new pumped hydro sites next to existing reservoirs (theconversation.com)

Read more https://theconversation.com/im-not-an-apologist-for-the-snowy-2-0-hydro-scheme-but-lets-not-obsess-over-the-delays-and-cost-blowouts-204915

The Times Features

Will the Wage Price Index growth ease financial pressure for households?

The Wage Price Index’s quarterly increase of 0.8% has been met with mixed reactions. While Australian wages continue to increase, it was the smallest increase in two and a half...

Back-to-School Worries? 70% of Parents Fear Their Kids Aren’t Ready for Day On

Australian parents find themselves confronting a key decision: should they hold back their child on the age border for another year before starting school? Recent research from...

Democratising Property Investment: How MezFi is Opening Doors for Everyday Retail Investors

The launch of MezFi today [Friday 15th November] marks a watershed moment in Australian investment history – not just because we're introducing something entirely new, but becaus...

Game of Influence: How Cricket is Losing Its Global Credibility

be losing its credibility on the global stage. As other sports continue to capture global audiences and inspire unity, cricket finds itself increasingly embroiled in political ...

Amazon Australia and DoorDash announce two-year DashPass offer only for Prime members

New and existing Prime members in Australia can enjoy a two-year membership to DashPass for free, and gain access to AU$0 delivery fees on eligible DoorDash orders New offer co...

6 things to do if your child’s weight is beyond the ideal range – and 1 thing to avoid

One of the more significant challenges we face as parents is making sure our kids are growing at a healthy rate. To manage this, we take them for regular check-ups with our GP...

Times Magazine

Enhance Software with Dynamic Code Analysis Techniques

Dynamic code analysis is a widely utilized technique that plays a crucial role in ensuring the reliability and security of software applications. This process involves the examination of an application's behaviour while it is executing, which is in c...

Google Ads Made Easy: Streamlining Your Online Advertising

Conquering the online marketplace in Melbourne can feel like climbing the Eureka Tower blindfolded. Yet the expanse of the Mornington Peninsula offers the perfect sanctuary for those of you who worry like me do. When used properly, Google Ads can a...

Things you need to know about certificate iii in mobile plant technology

g Certification is very important for all types of work in the industry. To succeed in the field, you need to complete the certification in the required field that you opt for. You can keep industrial technology working at peak capacity with certi...

Dog Breeder Charged with Inhumane Puppy Farming

Breeders of all kinds of puppies are very common nowadays with more people looking to care for their new little furry pals at home. But if you’re looking to get your first dog or are just looking to add another pup to the pack, you’ll want to make su...

Here are some great ways that you can support creative and curious children

A child’s learning doesn’t stop when they leave their classroom or daycare room. Children’s minds will develop faster in their first five years, than at any other time in their lives. It’s important for us as Educators, as well as parents to alwa...

Know all about Mobile App Advertising

Mobile app advertising is fast becoming a dominant tool that helps brands to reach their customers. It even beats television advertising in some countries. Most consumers spend more time on their smartphones rather than watching TV. If you wish to...