A short history of doomed second harbour crossing proposals for Auckland – and a quicker, cheaper option

  • Written by Timothy Welch, Senior Lecturer in Urban Planning, University of Auckland
A short history of doomed second harbour crossing proposals for Auckland – and a quicker, cheaper option

New Zealand is a small country that suddenly has big ideas about public transportation projects for its largest city. In February, the physical work[1] began for a partially tunnelled light rail line under the Auckland CBD that will eventually connect to the airport. The project could ultimately have a price tag nearing NZ$30 billion.

Things went big again last week with the release of five options[2] for a second harbour crossing. Four of the five will cost at least $20 billion and involve building another bridge and one or more tunnels for light rail and cars.

While the project is said to be on the fast track, with construction to begin in six years, Aucklanders would be forgiven if they didn’t buy into this timeline. The new options are just the latest in a long line of proposals that date back at least 35 years.

It’s worth reviewing the long and tumultuous history of second Auckland harbour crossing proposals. In the process, we might ask whether a sixth option might, in fact, be the best: apply congestion charging to the Auckland CBD, and give public transport, walking and cycling better access to the existing bridge.

The bridge is the main connection between Auckland’s CBD and its growing North Shore. Getty Images

Bridges and tunnels

The Auckland Harbour Bridge officially opened on May 30 1959. Construction[3] took four years and cost nearly $250 million (in today’s money), but the structure was already too narrow for traffic volumes. Within a decade, extra lanes built in Japan were bolted to the bridge – the so called “Nippon clip-ons[4]”.

From 1988 until 2010, various second crossing options were studied and presented, including:

  • 1988: a plan was developed for either tunnelled public transport or a second bridge

  • 1997: 11 options for a second crossing were studied and sent out for public consultation, including different tunnel or bridge alignments, with the most expensive option being a tunnel at roughly $2.6 billion in today’s dollars

  • 2003: a followup to the 1997 study suggested a combination of a second bridge and a tunnel, costed at around $4.5 billion in today’s dollars

  • 2008: a study of 159 crossing options was narrowed to three options[5], included either a new bridge or two possibilities for tunnels

  • 2010: a business case was developed[6] for three crossing options, including a second bridge, tunnelled heavy rail, and a tunnelled road, with the highest cost estimate just under $6 billion.

Walking and cycling

The original plans for the bridge had also included tolled cycle lanes, but these were eventually rejected for cost. In 2011, the idea was revived, with the New Zealand Transport Agency (now Waka Kotahi) announcing a “SkyPath[7]” plan to add walking and cycling lanes to the clip-ons. This was added to Auckland Transport’s strategic priority list the same year.

Resource consent for the SkyPath was lodged in 2015 and approved in 2016. The new Labour-led government in 2017 said it would fund the project, with a revised design for the path to sit on its own piers revealed in 2019.

Read more: Using valuable inner-city land for car parking? In a housing crisis, that just doesn’t add up[8]

In 2021 Waka Kotahi pulled the plug on the SkyPath plan, citing engineering complexity. The same year, a $685 million standalone cycling and walking bridge was announced. The cost estimate quickly rose to $785 million before it was cancelled[9] just four months later – but not before the government spent $51 million[10] on designs, consultants and engineering plan fees.

Since then, it has been a tale of stop-start (but mostly stop) initiatives, including:

November 2021: Waka Kotahi decided against[11] a cycling and walking “trial” across the bridge but endorsed a series of events for cyclists and walkers in December.

August 2022: Waka Kotahi announced a planned $700,000 one-day trial for walking and cycling would be scrapped, primarily citing concerns about the 6% bridge gradient allowing cyclists to reach speeds of 60km per hour and the potential for pedestrian collisions. (Ironically, one of the new cycling bridge options “would be of a similar gradient[12]” to the current bridge.)

December 2022: Waka Kotahi announced a series of “Walk it, Wheel it[13]” events for three Sundays in March for up to 60,000 Aucklanders to cross the bridge on foot or bike. But this was postponed in early 2023, with no future date announced.

Read more: Electric cars alone won’t save the planet. We'll need to design cities so people can walk and cycle safely[14]

Back to the future

The five new harbour crossing options are now out for public consultation[15], with a decision due by mid-year and construction to begin in 2029. But given the long history of studying, gathering feedback and then doing nothing about a second crossing (or improving public and active transport options on the existing bridge), some scepticism is warranted.

With projected finish dates ranging from 2039 to 2044, and costs up to $25 billion (assuming no delays or budget blowouts), the options also create more vehicle lanes just a few years before the Emission Reduction Plan[16]’s 2050 target for net zero emissions.

Read more: To get New Zealanders out of their cars we'll need to start charging the true cost of driving[17]

Surely a more sustainable solution would be to institute the long-discussed Auckland CBD congestion charge[18] and reallocate a few lanes on the existing bridge for public transport, cycling and walking.

This would reduce the number of CBD car trips and contribute to meeting those climate goals. If a second crossing is still needed, taking this more immediate action would at least offer additional – and more climate-friendly – travel options in the meantime.

Future-proofing part of Auckland’s transportation network may not require billions of dollars and decades of planning and construction. It could simply mean finally embracing a version of what was planned for the Auckland Harbour Bridge almost 65 years ago.

References

  1. ^ physical work (www.stuff.co.nz)
  2. ^ five options (www.nzta.govt.nz)
  3. ^ Construction (www.nzta.govt.nz)
  4. ^ Nippon clip-ons (teara.govt.nz)
  5. ^ narrowed to three options (www.nzta.govt.nz)
  6. ^ business case was developed (www.nzta.govt.nz)
  7. ^ SkyPath (www.greaterauckland.org.nz)
  8. ^ Using valuable inner-city land for car parking? In a housing crisis, that just doesn’t add up (theconversation.com)
  9. ^ cancelled (www.1news.co.nz)
  10. ^ government spent $51 million (www.newshub.co.nz)
  11. ^ Waka Kotahi decided against (www.nzta.govt.nz)
  12. ^ would be of a similar gradient (nzta.mysocialpinpoint.com)
  13. ^ Walk it, Wheel it (www.nzta.govt.nz)
  14. ^ Electric cars alone won’t save the planet. We'll need to design cities so people can walk and cycle safely (theconversation.com)
  15. ^ public consultation (nzta.mysocialpinpoint.com)
  16. ^ Emission Reduction Plan (environment.govt.nz)
  17. ^ To get New Zealanders out of their cars we'll need to start charging the true cost of driving (theconversation.com)
  18. ^ CBD congestion charge (www.rnz.co.nz)

Read more https://theconversation.com/a-short-history-of-doomed-second-harbour-crossing-proposals-for-auckland-and-a-quicker-cheaper-option-203140

Times Magazine

Headless CMS in Digital Twins and 3D Product Experiences

Image by freepik As the metaverse becomes more advanced and accessible, it's clear that multiple sectors will use digital twins and 3D product experiences to visualize, connect, and streamline efforts better. A digital twin is a virtual replica of ...

The Decline of Hyper-Casual: How Mid-Core Mobile Games Took Over in 2025

In recent years, the mobile gaming landscape has undergone a significant transformation, with mid-core mobile games emerging as the dominant force in app stores by 2025. This shift is underpinned by changing user habits and evolving monetization tr...

Understanding ITIL 4 and PRINCE2 Project Management Synergy

Key Highlights ITIL 4 focuses on IT service management, emphasising continual improvement and value creation through modern digital transformation approaches. PRINCE2 project management supports systematic planning and execution of projects wit...

What AI Adoption Means for the Future of Workplace Risk Management

Image by freepik As industrial operations become more complex and fast-paced, the risks faced by workers and employers alike continue to grow. Traditional safety models—reliant on manual oversight, reactive investigations, and standardised checklist...

From Beach Bops to Alpine Anthems: Your Sonos Survival Guide for a Long Weekend Escape

Alright, fellow adventurers and relaxation enthusiasts! So, you've packed your bags, charged your devices, and mentally prepared for that glorious King's Birthday long weekend. But hold on, are you really ready? Because a true long weekend warrior kn...

Effective Commercial Pest Control Solutions for a Safer Workplace

Keeping a workplace clean, safe, and free from pests is essential for maintaining productivity, protecting employee health, and upholding a company's reputation. Pests pose health risks, can cause structural damage, and can lead to serious legal an...

The Times Features

The Role of Your GP in Creating a Chronic Disease Management Plan That Works

Living with a long-term condition, whether that is diabetes, asthma, arthritis or heart disease, means making hundreds of small decisions every day. You plan your diet against m...

Troubleshooting Flickering Lights: A Comprehensive Guide for Homeowners

Image by rawpixel.com on Freepik Effectively addressing flickering lights in your home is more than just a matter of convenience; it's a pivotal aspect of both home safety and en...

My shins hurt after running. Could it be shin splints?

If you’ve started running for the first time, started again after a break, or your workout is more intense, you might have felt it. A dull, nagging ache down your shins after...

Metal Roof Replacement Cost Per Square Metre in 2025: A Comprehensive Guide for Australian Homeowners

In recent years, the trend of installing metal roofs has surged across Australia. With their reputation for being both robust and visually appealing, it's easy to understand thei...

Why You’re Always Adjusting Your Bra — and What to Do Instead

Image by freepik It starts with a gentle tug, then a subtle shift, and before you know it, you're adjusting your bra again — in the middle of work, at dinner, even on the couch. I...

How to Tell If Your Eyes Are Working Harder Than They Should Be

Image by freepik Most of us take our vision for granted—until it starts to let us down. Whether it's squinting at your phone, rubbing your eyes at the end of the day, or feeling ...