Renewable projects are getting built faster – but there’s even more need for speed 

  • Written by Thomas Longden, Senior Researcher, Urban Transformations Research Centre, Western Sydney University
Renewable projects are getting built faster – but there’s even more need for speed 

How long does it take to build a solar or wind farm? It’s a simple question with wide implications. To reach our ambitious 82% renewable energy target by 2030, we have to build many new projects – and start them soon.

In 2022, renewables hit a new high of 36% of Australia’s total electricity production, double that of 2017. That’s good – but there’s a long way to go.

Hitting the national target will require[1] building about 40 wind turbines (7 megawatts) every month, and 22,000 solar panels (500 watt) every day.

At the start of the year, climate minister Chris Bowen called on all levels of Australian government to speed up planning decisions[2] for renewable energy projects.

Reaching our target depends on one little-researched factor: completion time.

Solar and wind projects are built much faster than large fossil-energy plants. But the pre-construction approval process can be complex and slow projects down. In new research[3], my colleague and I found completion times have fallen significantly in recent years. But we need to go even faster to achieve the 2030 target.

Read more: Renewables are cheaper than ever yet fossil fuel use is still growing – here’s why[4]

How long does it take to complete renewable energy projects?

Very few studies have explored renewable energy lead times across a group of renewable projects in Australia or elsewhere. We investigated completion times for 170 onshore wind and solar projects completed in Australia between 2000 and 2023.

Using a data set we built[5], we found welcome news: Australian renewable projects are being built significantly faster.

Taking an onshore wind farm from idea to reality now takes about 53 months. This is substantially faster than wind farms started before 2016, which took more than 88 months. Obtaining pre-construction approvals and planning took up most of that time.

Solar projects now take about 41 months. It used to be double that, at up to 83 months before 2011.

Overall, there has been a decrease in solar lead times. Due to recent regulatory changes, the time taken for the construction and final stages has increased from 18 months to 21 months.

What does it take to build a solar or wind farm?

We break project lead times down into three stages:

1. Pre-construction – the developer designs the project and seeks approvals

2. Building and connecting – the time between starting construction and connecting to the grid to supply energy for the first time

3. Getting commissioned – this final stage involves obtaining a performance standard[6] from the Australian Energy Market Operator. Essentially, a new renewable plant has to be able to perform as expected and pass a series of tests. In our study, this stage starts at the time of first generation and finishes when a site generates at least 80% of its total capacity.

Why can lead times differ?

Passing through all three stages can be smooth – or fraught. While build times are improving, some projects can get stuck in development for years, making it seem harder than it is.

Delays can come from seeking approvals from multiple authorities and difficulties in accessing and connecting to the grid.

As lead times are rarely tracked across a large number of projects, outliers can skew how long we expect things take to complete. These outliers can get a lot of publicity[7].

Even when lead times are monitored and compared[8], the raw data isn’t made public. A renewable energy pipeline database should be public and provide historical examples for comparison. It could learn from the Australia and New Zealand Infrastructure Pipeline[9] and should track and compare lead times.

Read more: To hit 82% renewables in 8 years, we need skilled workers – and labour markets are already overstretched[10]

How did development speed up?

It wasn’t a single policy or process change that drove these faster build times. But the improvements in lead times were driven by faster pre-construction planning and approval stages.

We found clear evidence some states are faster than others. South Australia – Australia’s top renewable state – had notably lower pre-construction lead times for both wind and solar, likely due to streamlined approvals. We found some evidence of fast approvals for solar in Victoria.

Changes in project ownership occurred often (38% of projects) but this had little impact on how long they took to complete.

One issue that has increased lead times in Australia was a 2017 change to how renewables are tested, introduced as a response to the South Australia statewide blackout[11] of 2016. One aspect of this – the controversial “do no harm” system strength assessment – has since been removed[12].

These changes added an average of three months of delay for projects commencing construction after 2017.

We can go faster still

Even though Australian renewable lead times have shortened significantly since 2010, we should do more. After all, there are now only 71 months until 2030, when Australia’s renewables targets must be met.

Government approvals could be sped up if renewable developers can clearly see the steps to follow and deal with one central agency. All authorities involved should have maximum response times for key stages of the approval process.

Suitable projects located close to existing projects could also be assessed as expansions and not new developments. This would notably streamline the process. Authorities are already allowing developers to do this when approving grid-scale batteries to be installed near solar farms.

solar farm with battery
Speeding up approvals for battery projects next to existing renewable farms is possible. AAP

Why do we need this data?

If you’re a renewable energy developer, it’s vitally important to know how long it normally takes to get a project up and running. It’s also a key piece of data for investors and policymakers.

That’s why we have provided clear detail[13] of our data collection technique so it can be used by researchers, consultants, and government employees. Our data set is also available for download[14].

Is it still possible to hit 82% renewable energy by 2030? Yes – but based on our lead-time estimates, only if most projects start their planning phase in the next couple of years.

Read more: The road is long and time is short, but Australia's pace towards net zero is quickening[15]

References

  1. ^ will require (reneweconomy.com.au)
  2. ^ speed up planning decisions (www.smh.com.au)
  3. ^ new research (www.sciencedirect.com)
  4. ^ Renewables are cheaper than ever yet fossil fuel use is still growing – here’s why (theconversation.com)
  5. ^ data set we built (data.mendeley.com)
  6. ^ performance standard (aemo.com.au)
  7. ^ lot of publicity (www.abc.net.au)
  8. ^ monitored and compared (doi.org)
  9. ^ Australia and New Zealand Infrastructure Pipeline (infrastructurepipeline.org)
  10. ^ To hit 82% renewables in 8 years, we need skilled workers – and labour markets are already overstretched (theconversation.com)
  11. ^ statewide blackout (www.aer.gov.au)
  12. ^ since been removed (reneweconomy.com.au)
  13. ^ provided clear detail (doi.org)
  14. ^ available for download (data.mendeley.com)
  15. ^ The road is long and time is short, but Australia's pace towards net zero is quickening (theconversation.com)

Read more https://theconversation.com/renewable-projects-are-getting-built-faster-but-theres-even-more-need-for-speed-221874

Times Magazine

Building a Strong Online Presence with Katoomba Web Design

Katoomba web design is more than just creating a website that looks good—it’s about building an online presence that reflects your brand, engages your audience, and drives results. For local businesses in the Blue Mountains, a well-designed website a...

September Sunset Polo

International Polo Tour To Bridge Historic Sport, Life-Changing Philanthropy, and Breath-Taking Beauty On Saturday, September 6th, history will be made as the International Polo Tour (IPT), a sports leader headquartered here in South Florida...

5 Ways Microsoft Fabric Simplifies Your Data Analytics Workflow

In today's data-driven world, businesses are constantly seeking ways to streamline their data analytics processes. The sheer volume and complexity of data can be overwhelming, often leading to bottlenecks and inefficiencies. Enter the innovative da...

7 Questions to Ask Before You Sign IT Support Companies in Sydney

Choosing an IT partner can feel like buying an insurance policy you hope you never need. The right choice keeps your team productive, your data safe, and your budget predictable. The wrong choice shows up as slow tickets, surprise bills, and risky sh...

Choosing the Right Legal Aid Lawyer in Sutherland Shire: Key Considerations

Legal aid services play an essential role in ensuring access to justice for all. For people in the Sutherland Shire who may not have the financial means to pay for private legal assistance, legal aid ensures that everyone has access to representa...

Watercolor vs. Oil vs. Digital: Which Medium Fits Your Pet's Personality?

When it comes to immortalizing your pet’s unique personality in art, choosing the right medium is essential. Each artistic medium, whether watercolor, oil, or digital, has distinct qualities that can bring out the spirit of your furry friend in dif...

The Times Features

How much money do you need to be happy? Here’s what the research says

Over the next decade, Elon Musk could become the world’s first trillionaire[1]. The Tesla board recently proposed a US$1 trillion (A$1.5 trillion) compensation plan, if Musk ca...

NSW has a new fashion sector strategy – but a sustainable industry needs a federally legislated response

The New South Wales government recently announced the launch of the NSW Fashion Sector Strategy, 2025–28[1]. The strategy, developed in partnership with the Australian Fashion ...

From Garden to Gift: Why Roses Make the Perfect Present

Think back to the last time you gave or received flowers. Chances are, roses were part of the bunch, or maybe they were the whole bunch.   Roses tend to leave an impression. Even ...

Do I have insomnia? 5 reasons why you might not

Even a single night of sleep trouble can feel distressing and lonely. You toss and turn, stare at the ceiling, and wonder how you’ll cope tomorrow. No wonder many people star...

Wedding Photography Trends You Need to Know (Before You Regret Your Album)

Your wedding album should be a timeless keepsake, not something you cringe at years later. Trends may come and go, but choosing the right wedding photography approach ensures your ...

Can you say no to your doctor using an AI scribe?

Doctors’ offices were once private. But increasingly, artificial intelligence (AI) scribes (also known as digital scribes) are listening in. These tools can record and trans...