How can Aboriginal communities be part of the NSW renewable energy transition?

  • Written by Heidi Norman, Professor, Faculty of Arts and Social Sciences, University of Technology Sydney

The New South Wales government’s roadmap[1] to transition from coal-based electricity to renewable energy involves the creation of five “renewable energy zones[2]” across the state.

These “modern-day power stations[3]” will use solar, wind, batteries and new poles and wires to generate energy for the state. They’re part of a broader plan to meet a legislated target[4] of 12 gigawatts of renewable energy and 2 gigawatts of storage by 2030.

These renewable energy zones include measures to deliver regional benefits such as engagement, jobs and benefit-sharing with local Aboriginal communities. This is a first for an Australian renewable energy program of this scale.

However, two things are needed to maximise this opportunity for Aboriginal people.

First, Aboriginal land councils need greater support and resources to participate effectively in delivery of the renewable energy zones.

Second, there should be a program to facilitate the development of renewable energy projects on Aboriginal-owned land.

Through these actions, the government can help develop partnerships that can deliver revenue and jobs for Aboriginal communities as the state transitions to clean energy.

Read more: Traditional land burning is declining – here's why that's a problem[5]

Maximising opportunities for First Nations communities

There are some cases of renewable energy projects delivering for Aboriginal communities, such as solar farms engaging unemployed Aboriginal workers[6]. But overall the benefits have been limited to date.

However, legislation requires the NSW government bodies and renewables projects in the renewable energy zones to comply with “First Nations Guidelines” currently under development.

The guidelines will require:

  • regional reference groups
  • an engagement framework for renewable energy projects, and
  • a document reflecting community interests developed with the input of local Aboriginal organisations (land councils and Traditional Owners under Native Title) in each renewable energy zone.

Projects bidding for a “long-term energy supply agreement” from the NSW government - which will guarantee a minimum price for their output - have to comply with the Indigenous Procurement Policy[7]. This includes ensuring a minimum 1.5% Aboriginal workforce and 1.5% of contract value to Aboriginal businesses.

These First Nations guidelines will form part of the tender evaluation, creating incentives for projects to increase benefits for First Nations communities.

The inclusion of these First Nations guidelines in the renewable energy projects is a first for Australian renewable energy. It’s likely to significantly improve economic outcomes for Aboriginal communities.

So far, so good.

However, there are also some missed opportunities.

First, if renewable energy projects and the First Nations guidelines are to work well, greater resourcing and capacity-building is needed for local Aboriginal land councils[8] so they can participate effectively.

In addition, the NSW government should develop an Aboriginal-led local and regional level clean energy strategy so communities can identify what they want from this momentous change.

A study by the Indigenous Land and Justice Research Group[9], based at the University of Technology Sydney, revealed local Aboriginal land councils are eager for renewable energy. This would improve opportunities to live and work locally, boost energy security, lower costs, enable care of Country and create wealth.

However, the study found these communities had little or no knowledge about renewable energy options or how they could benefit.

Only one Local Aboriginal Land Council in the pilot renewable energy zone had prior dealings with renewable energy operators. All were uncertain about how their land assets could be mobilised.

Read more: A history of destruction: why the WA Aboriginal cultural heritage bill will not prevent another Juukan Gorge-like disaster[10]

More opportunities needed for Aboriginal-owned land in NSW

There are currently no measures to encourage and facilitate renewable energy projects on Aboriginal-owned land in NSW.

Work by Indigenous Energy Australia[11] and the Institute for Sustainable Futures found the best outcomes often occur from “mid-sized” renewable energy projects on Indigenous-owned land.

Examples include:

  • the Ramahyuck Solar Farm[12] (Longford, Victoria), which is wholly owned and operated by the Ramahyuck[13] District Aboriginal Corporation. Following government funding, debt financing was secured for construction. The profit generated from the development will be redirected to Aboriginal education and health programs

  • the Tuaropaki Geothermal Power Station[14] in New Zealand, which is 75% owned by the Māori, Tuaropaki Trust and 25% by Mercury Energy (a large energy company). The Tuaropaki Trust was developed through financial partnerships and government support. These developments produced long-term income for community programs and other commercial ventures

  • the Atlin Hydro Project[15] in Canada, a 100% Indigenous owned and operated project. Government support was critical in establishing the project. Once established, revenues were distributed based on joint clan meetings for health programs and a land guardian program.

Developing projects on Aboriginal-owned land would take more time to identify a workable model, ensure there is support within the land council and local community and develop local capacity. But done well, it can deliver greater benefits for Aboriginal communities.

A government program developed in parallel with the roll out of the renewable energy zones could develop opportunities for renewable energy developments in partnership with local Aboriginal land councils.

Support for meaningful, Aboriginal-led renewable energy projects on Aboriginal land has the potential to make real progress towards the long hoped for benefits of land restitution for First Peoples in NSW.

The time for action is now.

References

  1. ^ roadmap (www.energy.nsw.gov.au)
  2. ^ renewable energy zones (www.energy.nsw.gov.au)
  3. ^ modern-day power stations (www.energy.nsw.gov.au)
  4. ^ legislated target (www.theguardian.com)
  5. ^ Traditional land burning is declining – here's why that's a problem (theconversation.com)
  6. ^ engaging unemployed Aboriginal workers (esdnews.com.au)
  7. ^ Indigenous Procurement Policy (www.niaa.gov.au)
  8. ^ Aboriginal land councils (alc.org.au)
  9. ^ Indigenous Land and Justice Research Group (www.uts.edu.au)
  10. ^ A history of destruction: why the WA Aboriginal cultural heritage bill will not prevent another Juukan Gorge-like disaster (theconversation.com)
  11. ^ Indigenous Energy Australia (indigenousenergyaustralia.com)
  12. ^ the Ramahyuck Solar Farm (www.abc.net.au)
  13. ^ Ramahyuck (www.ramahyuck.org)
  14. ^ Tuaropaki Geothermal Power Station (tuaropaki.com)
  15. ^ Atlin Hydro Project (yukonenergy.ca)

Read more https://theconversation.com/how-can-aboriginal-communities-be-part-of-the-nsw-renewable-energy-transition-181171

Times Magazine

Understanding ITIL 4 and PRINCE2 Project Management Synergy

Key Highlights ITIL 4 focuses on IT service management, emphasising continual improvement and value creation through modern digital transformation approaches. PRINCE2 project management supports systematic planning and execution of projects wit...

What AI Adoption Means for the Future of Workplace Risk Management

Image by freepik As industrial operations become more complex and fast-paced, the risks faced by workers and employers alike continue to grow. Traditional safety models—reliant on manual oversight, reactive investigations, and standardised checklist...

From Beach Bops to Alpine Anthems: Your Sonos Survival Guide for a Long Weekend Escape

Alright, fellow adventurers and relaxation enthusiasts! So, you've packed your bags, charged your devices, and mentally prepared for that glorious King's Birthday long weekend. But hold on, are you really ready? Because a true long weekend warrior kn...

Effective Commercial Pest Control Solutions for a Safer Workplace

Keeping a workplace clean, safe, and free from pests is essential for maintaining productivity, protecting employee health, and upholding a company's reputation. Pests pose health risks, can cause structural damage, and can lead to serious legal an...

The Science Behind Reverse Osmosis and Why It Matters

What is reverse osmosis? Reverse osmosis (RO) is a water purification process that removes contaminants by forcing water through a semi-permeable membrane. This membrane allows only water molecules to pass through while blocking impurities such as...

Foodbank Queensland celebrates local hero for National Volunteer Week

Stephen Carey is a bit bananas.   He splits his time between his insurance broker business, caring for his young family, and volunteering for Foodbank Queensland one day a week. He’s even run the Bridge to Brisbane in a banana suit to raise mon...

The Times Features

My shins hurt after running. Could it be shin splints?

If you’ve started running for the first time, started again after a break, or your workout is more intense, you might have felt it. A dull, nagging ache down your shins after...

Metal Roof Replacement Cost Per Square Metre in 2025: A Comprehensive Guide for Australian Homeowners

In recent years, the trend of installing metal roofs has surged across Australia. With their reputation for being both robust and visually appealing, it's easy to understand thei...

Why You’re Always Adjusting Your Bra — and What to Do Instead

Image by freepik It starts with a gentle tug, then a subtle shift, and before you know it, you're adjusting your bra again — in the middle of work, at dinner, even on the couch. I...

How to Tell If Your Eyes Are Working Harder Than They Should Be

Image by freepik Most of us take our vision for granted—until it starts to let us down. Whether it's squinting at your phone, rubbing your eyes at the end of the day, or feeling ...

Ways to Attract Tenants in a Competitive Rental Market

In the kind of rental market we’ve got now, standing out is half the battle. The other half? Actually getting someone to sign that lease. With interest rates doing backflips and ...

Top Tips for Finding the Ideal Block to Build Your Home

There’s something deeply personal and exciting about building your own home. You’re not just choosing paint colours or furniture, you’re creating a space that reflects your lifes...